FORCE MAJEURE, HARDSHIP, IS THE UNION CONTRACT AIR TIGHT

Force Majeure (French for "superior force") is a common clause in contracts which essentially frees both parties from liability or obligation when an extraordinary event or circumstance beyond the control of the parties, such as a war, strike, riot, crime, or act of God (e.g., flooding, earthquake, volcano), prevents one or both parties from fulfilling their obligations under the contract. However, force majeure is not intended to excuse negligence or other malfeasance of a party, as where non-performance is caused by the usual and natural consequences of external forces (e.g., predicted rain stops an outdoor event), or where the intervening circumstances are specifically contemplated.


 

The House Hunter Buyer's Guide   (Advertisement)

The House Hunter Buyer’s Guide

  by Clifford S. Atkin
  ISBN13: 978-1-4134-3426-2 (Trade Paperback)
  ISBN: 1-4134-3426-6 (Trade Paperback)
  ISBN13: 978-1-4134-3427-9 (Hardback)
  ISBN: 1-4134-3427-4 (Hardback)
  Pages: 215

https://www2.xlibris.com/bookstore/bookdisplay.asp?bookid=21466 - 12k

From Wikipedia, the free encyclopedia          
Jump to: navigation, search

Hardship clause is a clause in a contract that is intended to cover cases in which unforeseen events occur that fundamentally alter the equilibrium of a contract resulting in an excessive burden being placed on one of the parties involved.[1]

Hardship clauses typically recognize that parties must perform their contractual obligations even if events have rendered performance more onerous than would reasonably have been anticipated at the time of the conclusion of the contract. However, where continued performance has become excessively burdensome due to an event beyond a party’s reasonable control which it could not reasonably have been expected to have taken into account, the clause can obligate the parties to negotiate alternative contractual terms which reasonably allow for the consequences of the event.

[edit] Relation to force majeure

The hardship clause is sometimes used in relation to force majeure, particularly due the fact that they share similar features and they both cater to situations of changed circumstances. The difference between the two concepts is that hardship is where the performance of the disadvantaged party has become much more burdensome, but not impossible, while force majeure refers to a party's contractual requirements have become impossible, at least temporarily. Hardship constitutes a reason for a change in the contractual program of the parties. The aim of the parties remains to implement the contract. Force majeure, however, is situated in the context of non-performance, and deals with the suspension or termination of the contract.[2]

 

What did you think of this article?




Trackbacks
  • No trackbacks exist for this post.
Comments
  • No comments exist for this post.
Leave a comment

Submitted comments are subject to moderation before being displayed.

 Name

 Email (will not be published)

 Website

Your comment is 0 characters limited to 3000 characters.